Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 7 Question 97 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 97
Topic #: 7
[All PMI-RMP Questions]

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Olen
27 days ago
D sounds good, but a schedule buffer is more of a Band-Aid than a real solution. You need to address the root cause, which is lack of stakeholder engagement.
upvoted 0 times
...
Sean
1 months ago
Haha, I bet the end user who strongly opposed the release was just looking for a reason to complain. Some people are never satisfied, no matter what you do!
upvoted 0 times
Ellen
15 days ago
C) Performed proper risk identification at the project outset to ensure this risk was identified and mitigated.
upvoted 0 times
...
Dana
20 days ago
A) Engaged the sponsor and informed them of the decision to remove the planned feature.
upvoted 0 times
...
...
Marylyn
1 months ago
C seems like the most appropriate answer to me. Proper risk identification at the beginning could have helped them anticipate this issue and plan accordingly.
upvoted 0 times
Skye
12 days ago
I agree, if they had identified this risk earlier, they could have come up with a better plan to address it.
upvoted 0 times
...
Chaya
25 days ago
C seems like the most appropriate answer to me. Proper risk identification at the beginning could have helped them anticipate this issue and plan accordingly.
upvoted 0 times
...
...
Gretchen
1 months ago
I believe performing proper risk identification at the project outset would have been the best approach to prevent this issue.
upvoted 0 times
...
Edgar
2 months ago
I agree with Rueben. Getting buy-in and support from stakeholders is crucial to prevent such situations.
upvoted 0 times
...
Craig
2 months ago
I think the answer is B. Engaging the stakeholders more in risk management would have been the best way to prevent this situation. Stakeholder buy-in is crucial for managing risks effectively.
upvoted 0 times
Christoper
2 months ago
B) Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.
upvoted 0 times
...
Hester
2 months ago
A) Engaged the sponsor and informed them of the decision to remove the planned feature.
upvoted 0 times
...
...
Rueben
2 months ago
I think the risk manager should have engaged the stakeholders more in risk management activities.
upvoted 0 times
...

Save Cancel