Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 7 Question 97 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 97
Topic #: 7
[All PMI-RMP Questions]

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Edgar
14 days ago
I agree with Rueben. Getting buy-in and support from stakeholders is crucial to prevent such situations.
upvoted 0 times
...
Craig
15 days ago
I think the answer is B. Engaging the stakeholders more in risk management would have been the best way to prevent this situation. Stakeholder buy-in is crucial for managing risks effectively.
upvoted 0 times
Christoper
8 days ago
B) Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.
upvoted 0 times
...
Hester
10 days ago
A) Engaged the sponsor and informed them of the decision to remove the planned feature.
upvoted 0 times
...
...
Rueben
20 days ago
I think the risk manager should have engaged the stakeholders more in risk management activities.
upvoted 0 times
...

Save Cancel