BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 7 Question 85 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 85
Topic #: 7
[All PMI-RMP Questions]

Harry works as a project manager for the NHQ Project. He is performing quantitative risk analysis for his project. One of the project risks has a 40 percent probability of happening, and it will cost the project $65,000 if the risk happens. What is the expected monetary value of this risk event?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Jenifer
1 months ago
This is easy peasy! The expected monetary value is the probability of the risk event multiplied by the cost if it happens. So, D) $27,000 is the way to go. Now, where's the coffee machine? I need a boost after all this brain power.
upvoted 0 times
...
Nickolas
1 months ago
I'm feeling lucky today, so I'll go with A) Negative $26,000. Just kidding, I know the right answer is D) $27,000. Not too hard of a question, really.
upvoted 0 times
...
Mila
1 months ago
C) Zero - the risk event has not yet occurred? What kind of answer is that? Of course, the expected monetary value is not zero just because the risk hasn't happened yet. Gotta be more logical than that.
upvoted 0 times
Loreta
16 days ago
C) Zero - the risk event has not yet occurred
upvoted 0 times
...
Marget
26 days ago
D) $27,000
upvoted 0 times
...
Marva
29 days ago
B) Negative $67,000
upvoted 0 times
...
Myra
1 months ago
A) Negative $26,000
upvoted 0 times
...
...
Luis
2 months ago
I'm going with B) Negative $67,000. Why would the expected monetary value be positive if the risk event has a negative impact on the project?
upvoted 0 times
Wilburn
1 months ago
The expected monetary value is actually D) $27,000 because it takes into account the probability and cost of the risk event.
upvoted 0 times
...
Teddy
1 months ago
I'm going with B) Negative $67,000. Why would the expected monetary value be positive if the risk event has a negative impact on the project?
upvoted 0 times
...
Julie
1 months ago
I think the expected monetary value is D) $27,000.
upvoted 0 times
...
...
Ashlee
2 months ago
I agree with Angelo, the expected monetary value is $27,000.
upvoted 0 times
...
Angelo
2 months ago
I think it's option D) $27,000 because it's the probability multiplied by the cost.
upvoted 0 times
...
Francisca
2 months ago
Hmm, I think the correct answer is D) $27,000. The expected monetary value is calculated by multiplying the probability of the risk event (40%) by the cost if the risk event occurs ($65,000), which equals $26,000.
upvoted 0 times
Arthur
2 months ago
Thanks for the explanation, I understand now.
upvoted 0 times
...
Tijuana
2 months ago
Yes, the expected monetary value is $27,000.
upvoted 0 times
...
Xochitl
2 months ago
That's correct! The expected monetary value is $27,000.
upvoted 0 times
...
Armando
2 months ago
I agree, the correct answer is D) $27,000.
upvoted 0 times
...
Leonor
2 months ago
I think the correct answer is D) $27,000.
upvoted 0 times
...
...
Suzan
3 months ago
What is the expected monetary value of the risk event?
upvoted 0 times
...

Save Cancel