Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 7 Question 83 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 83
Topic #: 7
[All PMI-RMP Questions]

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Lelia
2 days ago
The risk manager should have engaged with the project sponsor before presenting to the board.
upvoted 0 times
...

Save Cancel