Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 7 Question 72 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 72
Topic #: 7
[All PMI-RMP Questions]

A project is delayed and the risk manager is working on a new plan for the remaining work Based on previous results the project team is having frequent issues with quality due to lack of experience in the technology used, requiring additional testing effort and rework.

How should the risk manager and team respond to this type of risk in the future?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel