Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 7 Question 28 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 28
Topic #: 7
[All PMI-RMP Questions]

Consider the risk probability-impact matrix in the figure given below:

If Risk B happens in this project, how much will be left in the contingency reserve?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel