Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 6 Question 94 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 94
Topic #: 6
[All PMI-RMP Questions]

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Susana
7 days ago
I think the risk manager should close and communicate the results of the risk response actions.
upvoted 0 times
...

Save Cancel