BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 6 Question 59 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 59
Topic #: 6
[All PMI-RMP Questions]

Frances is the project manager of a project in her organization. This project has a budget of $567,000 and is schedule to last for three years. Frances wants to examine the risk events to determine which risk events have the most potential impact on the project. Which modeling technique can help Frances to accomplish this goal?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel