Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 5 Question 64 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 64
Topic #: 5
[All PMI-RMP Questions]

A risk manager has to Inform a project sponsor of the expected duration of an entire project. The project has three main tasks, each with different probabilities of duration. Which analytical tool should the risk manager use?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Jordan
3 days ago
I think the risk manager should use Monte Carlo simulation.
upvoted 0 times
...

Save Cancel