Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 4 Question 66 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 66
Topic #: 4
[All PMI-RMP Questions]

During project execution tor a software development program a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Malcom
2 hours ago
I think the risk manager should review the assumptions to understand any change.
upvoted 0 times
...

Save Cancel