BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 4 Question 47 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 47
Topic #: 4
[All PMI-RMP Questions]

Adrian is a project manager for a new project using a technology that has recently been released and there's relatively little information about the technology. Initial testing of the technology makes the use of it look promising, but there's still uncertainty as to the longevity and reliability of the technology. Adrian wants to consider the technology factors a risk for her project. Where should she document the risks associated with this technology so she can track the risk status and responses?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel