Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 2 Question 79 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 79
Topic #: 2
[All PMI-RMP Questions]

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Delsie
1 days ago
I think the risk manager should analyze the risks and add them to the risk register to continue the process.
upvoted 0 times
...

Save Cancel