A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.
What should the risk manager do next?
Oliva
21 days agoMarti
25 days agoAlesia
26 days agoTheron
27 days agoBrianne
7 days agoBeckie
13 days agoJess
1 months agoMyrtie
12 days agoKris
16 days agoCristy
24 days agoMelvin
1 months agoMaricela
19 days agoSarah
24 days agoCaprice
1 months agoTerrilyn
1 months ago