Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 95 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 95
Topic #: 10
[All PMI-RMP Questions]

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Melvin
10 days ago
B) Assess the impact of residual and secondary risks on project objectives. We need to understand how these risks might affect the overall project, not just the initial ones.
upvoted 0 times
Caprice
2 days ago
User 1: We should definitely assess the impact of those secondary risks on our project objectives.
upvoted 0 times
...
...
Terrilyn
11 days ago
I think the risk manager should assess the impact of residual and secondary risks on project objectives.
upvoted 0 times
...

Save Cancel