Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 95 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 95
Topic #: 10
[All PMI-RMP Questions]

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Oliva
21 days ago
I believe assessing the risk register to ensure the secondary risks are realistic is also crucial. We need to make sure we are addressing all potential risks.
upvoted 0 times
...
Marti
25 days ago
Haha, the risk manager should also assess the team's caffeine intake to see if that's causing any secondary risks!
upvoted 0 times
...
Alesia
26 days ago
I agree with Terrilyn. It's important to understand how these risks could affect the project outcomes.
upvoted 0 times
...
Theron
27 days ago
C) Assess the change log to establish that changes were implemented. Ensuring the changes were correctly implemented is key to managing the risks.
upvoted 0 times
Brianne
7 days ago
C) Assess the change log to establish that changes were implemented.
upvoted 0 times
...
Beckie
13 days ago
B) Assess the impact of residual and secondary risks on project objectives.
upvoted 0 times
...
...
Jess
1 months ago
I agree with Melvin. Identifying secondary risks is crucial, but we need to evaluate their potential impact to make informed decisions.
upvoted 0 times
Myrtie
12 days ago
User 3: Let's make sure we evaluate the potential impact before moving forward.
upvoted 0 times
...
Kris
16 days ago
User 2: Agreed, that's crucial for making informed decisions.
upvoted 0 times
...
Cristy
24 days ago
User 1: We need to assess the impact of residual and secondary risks on project objectives.
upvoted 0 times
...
...
Melvin
1 months ago
B) Assess the impact of residual and secondary risks on project objectives. We need to understand how these risks might affect the overall project, not just the initial ones.
upvoted 0 times
Maricela
19 days ago
User 3: It's important to consider all potential risks, not just the initial ones.
upvoted 0 times
...
Sarah
24 days ago
User 2: Agreed, we need to make sure we understand how they could affect the overall project.
upvoted 0 times
...
Caprice
1 months ago
User 1: We should definitely assess the impact of those secondary risks on our project objectives.
upvoted 0 times
...
...
Terrilyn
1 months ago
I think the risk manager should assess the impact of residual and secondary risks on project objectives.
upvoted 0 times
...

Save Cancel