Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 93 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 93
Topic #: 10
[All PMI-RMP Questions]

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Merilyn
1 months ago
D) Escalate the project risks to upper management. Yep, time to let the big shots handle this one. I bet they'll love that.
upvoted 0 times
Lonny
19 days ago
B) Review the effectiveness of the risk process.
upvoted 0 times
...
Lavina
21 days ago
A) Create a new project plan including the new risks.
upvoted 0 times
...
...
Dierdre
2 months ago
A) Create a new project plan including the new risks. Sounds like a good idea to me. Gotta stay on top of those curveballs, am I right?
upvoted 0 times
...
Tracey
2 months ago
C) Update the risk management plan. Duh, that's project management 101. Didn't they teach you that in your fancy certification course?
upvoted 0 times
Joni
8 days ago
D) Escalate the project risks to upper management.
upvoted 0 times
...
Nichelle
9 days ago
C) Update the risk management plan.
upvoted 0 times
...
Cherrie
11 days ago
B) Review the effectiveness of the risk process.
upvoted 0 times
...
Colette
17 days ago
A) Create a new project plan including the new risks.
upvoted 0 times
...
...
Marisha
2 months ago
B) Review the effectiveness of the risk process. Gotta find out where things went wrong and learn from it. Hindsight is 20/20, right?
upvoted 0 times
Catalina
2 months ago
D) Escalate the project risks to upper management.
upvoted 0 times
...
Rosalyn
2 months ago
C) Update the risk management plan.
upvoted 0 times
...
Tiffiny
2 months ago
B) Review the effectiveness of the risk process.
upvoted 0 times
...
Luisa
2 months ago
A) Create a new project plan including the new risks.
upvoted 0 times
...
...
Tayna
2 months ago
I believe escalating the project risks to upper management is the best option. They need to be aware of the situation.
upvoted 0 times
...
Galen
2 months ago
I agree with Francis. It's important to see if there are any gaps in the risk management plan.
upvoted 0 times
...
Mable
2 months ago
D) Escalate the project risks to upper management. That's the obvious choice here. Can't let those executives off the hook, you know?
upvoted 0 times
Rodolfo
1 months ago
D) Escalate the project risks to upper management.
upvoted 0 times
...
Ricarda
2 months ago
B) Review the effectiveness of the risk process.
upvoted 0 times
...
Kayleigh
2 months ago
C) Update the risk management plan.
upvoted 0 times
...
Alpha
2 months ago
A) Create a new project plan including the new risks.
upvoted 0 times
...
...
Francis
2 months ago
I think the risk manager should review the effectiveness of the risk process.
upvoted 0 times
...

Save Cancel