During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.
What should the risk manager do?
Frederic
1 months agoHannah
4 days agoRosalia
5 days agoGary
6 days agoNickie
14 days agoMakeda
1 months agoCarylon
1 months agoGilberto
2 days agoErick
10 days agoNicolette
15 days agoEugene
2 months agoLisha
15 days agoSuzan
1 months agoColeen
1 months agoKrystina
2 months agoAshanti
2 months agoReuben
2 months agoAhmed
2 months agoNu
18 days agoRobt
19 days agoZita
2 months agoHassie
2 months agoKarol
2 months ago