BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 92 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 92
Topic #: 10
[All PMI-RMP Questions]

You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Tiffiny
19 hours ago
Wow, this is a tough one. I'm going with C) Pure risk. The contractor's failure to complete the work on time is an unpredictable and uncontrollable risk, right?
upvoted 0 times
...
Cecily
2 days ago
B) Secondary risk. The delay in the contractor's work could lead to other issues down the line. That's a secondary risk event.
upvoted 0 times
...
Yuette
16 days ago
I agree with Pearline. Transferring the risk to the contractor is the best option in this situation.
upvoted 0 times
...
Leanna
22 days ago
D) Transference, for sure. The project manager is transferring the risk of the dangerous activity to the licensed contractor.
upvoted 0 times
Dominque
22 hours ago
D) Transference
upvoted 0 times
...
Ciara
2 days ago
C) Pure risk
upvoted 0 times
...
Jettie
7 days ago
A) Internal
upvoted 0 times
...
Nickolas
12 days ago
B) Secondary risk
upvoted 0 times
...
Gwen
14 days ago
A) Internal
upvoted 0 times
...
...
Pearline
25 days ago
I think the answer is D) Transference.
upvoted 0 times
...

Save Cancel