Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 92 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 92
Topic #: 10
[All PMI-RMP Questions]

You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Paris
20 days ago
The contractor better not try to pull a fast one and claim their dog ate the project schedule. That's not how this works!
upvoted 0 times
Anna
3 days ago
Let's communicate clearly with the contractor about the importance of meeting the project schedule.
upvoted 0 times
...
Joseph
4 days ago
We should have a contingency plan in place in case the contractor does not meet the deadline.
upvoted 0 times
...
Floyd
8 days ago
If the contractor falls behind schedule, it could impact our entire project timeline.
upvoted 0 times
...
Eva
13 days ago
We need to closely monitor the contractor's progress to ensure they stay on track.
upvoted 0 times
...
...
Brunilda
25 days ago
Hmm, I'm torn between B) and D). Guess I'll just roll the dice and go with D). What could go wrong?
upvoted 0 times
...
Tiffiny
1 months ago
Wow, this is a tough one. I'm going with C) Pure risk. The contractor's failure to complete the work on time is an unpredictable and uncontrollable risk, right?
upvoted 0 times
Lisha
8 days ago
B: Absolutely, we can't afford any delays in the project timeline.
upvoted 0 times
...
Marvel
16 days ago
A: We'll just have to monitor the situation closely and have a backup plan in place.
upvoted 0 times
...
Leana
19 days ago
B: Yeah, I agree. It's definitely an unpredictable and uncontrollable event.
upvoted 0 times
...
Rodolfo
20 days ago
A: I think you're right. It sounds like a pure risk to me too.
upvoted 0 times
...
...
Cecily
1 months ago
B) Secondary risk. The delay in the contractor's work could lead to other issues down the line. That's a secondary risk event.
upvoted 0 times
Karan
12 days ago
C) Residual risk. Even after hiring the contractor, there is still a risk of delays in subsequent work.
upvoted 0 times
...
Gladis
15 days ago
B) Secondary risk. The delay in the contractor's work could lead to other issues down the line. That's a secondary risk event.
upvoted 0 times
...
Nydia
23 days ago
A) Primary risk. The initial decision to hire the contractor was the primary risk event.
upvoted 0 times
...
...
Yuette
2 months ago
I agree with Pearline. Transferring the risk to the contractor is the best option in this situation.
upvoted 0 times
...
Leanna
2 months ago
D) Transference, for sure. The project manager is transferring the risk of the dangerous activity to the licensed contractor.
upvoted 0 times
Ethan
8 days ago
D) Transference
upvoted 0 times
...
Claudio
9 days ago
C) Pure risk
upvoted 0 times
...
Kathrine
15 days ago
B) Secondary risk
upvoted 0 times
...
Dante
29 days ago
D) Transference, for sure. The project manager is transferring the risk of the dangerous activity to the licensed contractor.
upvoted 0 times
...
Dominque
1 months ago
D) Transference
upvoted 0 times
...
Ciara
1 months ago
C) Pure risk
upvoted 0 times
...
Jettie
1 months ago
A) Internal
upvoted 0 times
...
Nickolas
1 months ago
B) Secondary risk
upvoted 0 times
...
Gwen
1 months ago
A) Internal
upvoted 0 times
...
...
Pearline
2 months ago
I think the answer is D) Transference.
upvoted 0 times
...

Save Cancel