A project baseline included a budget of USS900 million and a 12-month schedule. Three months into the project a risk manager collected performance data on the project expenditure showing an actual cumulative lost.
What should the risk manager use to ascertain the cost performance risk?
Yuette
1 months agoHoward
11 days agoBong
14 days agoJonell
17 days agoDerick
2 months agoAndree
2 days agoRebecka
4 days agoSuzan
6 days agoMaybelle
2 months agoDierdre
2 months agoVerona
3 months agoVon
1 months agoJessenia
1 months agoRonnie
1 months agoPolly
1 months agoTarra
3 months agoFrance
3 months agoJerrod
3 months agoCiara
3 months agoNovella
3 months ago