Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 69 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 69
Topic #: 10
[All PMI-RMP Questions]

A project baseline included a budget of USS900 million and a 12-month schedule. Three months into the project a risk manager collected performance data on the project expenditure showing an actual cumulative lost.

What should the risk manager use to ascertain the cost performance risk?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel