BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-PBA Topic 9 Question 53 Discussion

Actual exam question for PMI's PMI-PBA exam
Question #: 53
Topic #: 9
[All PMI-PBA Questions]

The stakeholders for a newly approved project are subject matter experts who are very knowledgeable in the client's business and will provide the project requirements. The project team scheduled separate sessions with each subject matter expert to identify and prioritize the requirements.

Which technique is being used?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel