Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-PBA Topic 8 Question 89 Discussion

Actual exam question for PMI's PMI-PBA exam
Question #: 89
Topic #: 8
[All PMI-PBA Questions]

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.

The business analyst tells the stakeholder that the requirement status was changed to "deferred ''

What could have prevented the stakeholder from being surprised about the status change?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Jamika
8 hours ago
I can't believe the requirement was deferred without us knowing.
upvoted 0 times
...

Save Cancel