Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-PBA Topic 6 Question 77 Discussion

Actual exam question for PMI's PMI-PBA exam
Question #: 77
Topic #: 6
[All PMI-PBA Questions]

A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Arlette
1 days ago
I think we should use the MoSCoW technique to prioritize the requirements.
upvoted 0 times
...

Save Cancel