Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-PBA Topic 6 Question 73 Discussion

Actual exam question for PMI's PMI-PBA exam
Question #: 73
Topic #: 6
[All PMI-PBA Questions]

After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule. The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.

Which prioritization technique should the business analyst use?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel