A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.
What should the business analyst do immediately after the discussion?
I'm surprised D isn't the correct answer. Assessing risks should be a top priority for any project manager. Maybe the business analyst can do that while they're talking to the process owners?
C is a good idea, but it's not the immediate next step. The business analyst should focus on understanding the project first before developing an issues log.
B sounds like a good idea, but I think A is the best choice. You can't put the information into a project plan without first talking to the process owners.
I think the correct answer is A. The business analyst should schedule time with the process owners to get a better understanding of the project's impact on the marketing and procurement units.
Viva
7 days agoJohna
8 days agoChantell
9 days agoMargart
5 days agoDomonique
18 days agoKatlyn
20 days agoDewitt
29 days agoDaron
1 months agoBasilia
12 days agoTruman
15 days agoLatosha
19 days agoAnika
1 months agoDarell
2 days agoBrock
8 days agoAzalee
8 days agoCelestina
12 days agoSheron
1 months agoMelissia
1 months agoIlene
2 months ago