PMI Exam PMI-PBA Topic 4 Question 19 Discussion

Actual exam question for PMI's PMI-PBA exam
Question #: 19
Topic #: 4
[All PMI-PBA Questions]

A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product.

Which of the following documents should be used?

Show Suggested Answer Hide Answer
Suggested Answer: A