Question #: 22
Topic #: 3
[All PMI-PBA Questions]

A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.

What document should the business analyst use to determine the relationship of the requirement to the business need?

Show Suggested Answer Hide Answer
Suggested Answer: B