PMI Exam PMI-ACP Topic 9 Question 68 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 68
Topic #: 9
[All PMI-ACP Questions]

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories. What should the scrum master do?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts: