Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 8 Question 73 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 73
Topic #: 8
[All PMI-ACP Questions]

A projects first iteration contains item

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Percy
7 months ago
I think we should escalate the issue to the customer and get their approval before starting the design of item B.
upvoted 0 times
...
Kate
7 months ago
It's true, but we need to consider the risk of impacting the first iteration even more.
upvoted 0 times
...
Beckie
7 months ago
But what if starting the design of item B can actually help speed up the second iteration?
upvoted 0 times
...
Percy
7 months ago
Agreed, we need to focus on getting the first iteration back on track.
upvoted 0 times
...
Kate
7 months ago
I think we should defer starting the design of item B.
upvoted 0 times
...
Cordelia
7 months ago
I think we should escalate the issue to the customer and obtain their approval before starting the design of item B to avoid any conflicts later.
upvoted 0 times
...
Alesia
7 months ago
I agree with Aretha. It's better to defer starting the design of item B to avoid impacting the second iteration further.
upvoted 0 times
...
Earleen
7 months ago
I disagree. We should proceed with the design of item B to hasten the second iteration.
upvoted 0 times
...
Aretha
7 months ago
I think we should defer starting the design of item B until the second iteration is being planned.
upvoted 0 times
...
Lera
8 months ago
Hmm, I'm not so sure. Option B does seem tempting, especially if we're already behind schedule. But I agree, we need to be careful about scope creep. Maybe we could compromise and do a bit of preliminary design on item B, just to get a head start, but not fully commit to it until the second iteration?
upvoted 0 times
...
Corrina
8 months ago
You know, I was just thinking the same thing. Deferring the design of item B is probably the safest bet. We don't want to end up in a situation where we're trying to cram too much in and end up with a subpar product.
upvoted 0 times
Kimberely
7 months ago
C) Escalate the issue to the customer and obtain their approval before starting the design of item B
upvoted 0 times
...
Vallie
8 months ago
Agreed, it's better to prioritize and not risk compromising the quality of the product.
upvoted 0 times
...
Clare
8 months ago
A) Defer starting the design of item B until the second iteration is being planned
upvoted 0 times
...
Stephaine
8 months ago
I disagree, rushing into item B could create more problems in the long run.
upvoted 0 times
...
Paris
8 months ago
B) Proceed with the design of item B, since it will hasten the second iteration
upvoted 0 times
...
Eleonore
8 months ago
You're right, focusing on item A first before moving on to B makes sense.
upvoted 0 times
...
Arlene
8 months ago
A) Defer starting the design of item B until the second iteration is being planned
upvoted 0 times
...
...
Stevie
8 months ago
I agree, this is a tough one. On the one hand, we want to try and stay on schedule, but on the other, we don't want to risk the quality of the deliverables. Maybe we should consider option A and defer the design of item B until the second iteration is being planned.
upvoted 0 times
...
Alberta
8 months ago
Hmm, this is a tricky one. I can see the logic behind starting the design of item B early to try and catch up, but I'm not sure that's the best approach. We need to be careful about scope creep and making sure we don't overcommit ourselves.
upvoted 0 times
...

Save Cancel