BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 6 Question 58 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 58
Topic #: 6
[All PMI-ACP Questions]

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so tar on the project How should the agile practitioner explain to server management the benefits of this approach?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel