Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 6 Question 54 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 54
Topic #: 6
[All PMI-ACP Questions]

A newly formed development learn experienced difficulty with accurately estimating product backlog items As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations

What should the team do to improve the accuracy of their estimates?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel