BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 6 Question 50 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 50
Topic #: 6
[All PMI-ACP Questions]

A project Worn meets to estimate user stones for a sprint. While an important non-functional requirement must be delivered in the sprint the estimate exceeds sprint capacity.

What should the team do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel