BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 5 Question 45 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 45
Topic #: 5
[All PMI-ACP Questions]

A learn member on a new scrum project previously provided support lo another application Due to issues with that application the team member's former supervisor continues assigning them tasks related to that protect The new project's scrum master includes this issue in the risk register.

What should the scrum master do next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel