Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 2 Question 98 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 98
Topic #: 2
[All PMI-ACP Questions]

Exhibit:

Based on the backlog metrics in the chart, what can explain the Jump in points at the end of iteration 4?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

I agree, Option C makes the most sense. It's common for teams to discover underestimated stories and need to adjust the points accordingly.
upvoted 0 times
...
Devora
1 days ago
Option C looks like the correct answer here. The team probably realized that some stories were underestimated and needed to re-estimate them.
upvoted 0 times
...
Ronnie
9 days ago
That's a good point, Alberta. Improvements in work could definitely lead to added story points.
upvoted 0 times
...
Alberta
12 days ago
I believe the team might have discovered improvements in previously accepted work.
upvoted 0 times
...
Ellen
26 days ago
I agree with Ronnie, underestimation of stories could explain the increase in points.
upvoted 0 times
...
Ronnie
29 days ago
I think the jump in points could be due to underestimation of some stories.
upvoted 0 times
...

Save Cancel