BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 2 Question 89 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 89
Topic #: 2
[All PMI-ACP Questions]

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this

What should the team do next?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Gwenn
1 months ago
I think applying the 80/20 rule could also be a good approach. It ensures that we allocate some capacity for risk mitigation in each sprint.
upvoted 0 times
...
Celestina
1 months ago
I agree with Gwenn. It's important to address the risks proactively to prevent them from becoming issues.
upvoted 0 times
...
Yasuko
2 months ago
Haha, D is like burying your head in the sand. Waiting for issues to arise and then dealing with them? No thanks, I'd rather be prepared.
upvoted 0 times
...
Yun
2 months ago
Hmm, I'm not sure about that. C looks interesting - reserving 20% of each sprint for risk mitigation could be a good safety net.
upvoted 0 times
Evelynn
13 days ago
Hmm, I'm not sure about that. C looks interesting - reserving 20% of each sprint for risk mitigation could be a good safety net.
upvoted 0 times
...
Trinidad
15 days ago
C) Apply the 80/20 rule, reserving 20 percent of each sprint's capacity for risk mitigation.
upvoted 0 times
...
Maryln
17 days ago
B) Add risk mitigation time to each requirement.
upvoted 0 times
...
Esteban
23 days ago
C) Apply the 80/20 rule, reserving 20 percent of each sprints capacity for risk mitigation.
upvoted 0 times
...
Luann
26 days ago
B) Add risk mitigation time to each requirement.
upvoted 0 times
...
Galen
28 days ago
A) Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints.
upvoted 0 times
...
Hildegarde
1 months ago
A) Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints.
upvoted 0 times
...
...
Gwenn
2 months ago
We should add risk mitigation tasks to the backlog and prioritize them in the sprints.
upvoted 0 times
...
Nohemi
2 months ago
A is the way to go. Adding specific risk mitigation tasks to the backlog is the best approach to address the increased risk profile.
upvoted 0 times
Kanisha
1 months ago
B) I agree, it's important to address the risks proactively rather than waiting for them to become issues.
upvoted 0 times
...
Azzie
2 months ago
A) Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints.
upvoted 0 times
...
...
Cecil
2 months ago
I agree with Nohemi. Option A seems like the most proactive and systematic way to handle the situation.
upvoted 0 times
...

Save Cancel