Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 11 Question 85 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 85
Topic #: 11
[All PMI-ACP Questions]

A technical problem arises that win likely impact the stories planned for delivery in the current sprint What should the scrum master do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Avery
2 months ago
This question is a real head-scratcher, but at least it's not as bad as the one about the Scrum Master who tried to juggle a few Sprints at once. Talk about a circus!
upvoted 0 times
Pansy
2 months ago
D) Engage a technical manager to assist With finding a solution
upvoted 0 times
...
Edwin
2 months ago
A) Consider adding a story to the next sprint to seek resolution
upvoted 0 times
...
Gayla
2 months ago
C) Ask the team to collaboratively work out a solution
upvoted 0 times
...
...
Erasmo
3 months ago
Engaging a technical manager to assist could also be helpful in finding a solution.
upvoted 0 times
...
Annice
3 months ago
I think adding a story to the next sprint could be a good option to seek resolution.
upvoted 0 times
...
Fernanda
3 months ago
Option D seems like the easy way out. If we need a technical manager to solve our problems, we might as well not bother with Scrum at all!
upvoted 0 times
Margurite
2 months ago
C: Adding a story to the next sprint could also help address the issue.
upvoted 0 times
...
Stephanie
2 months ago
B: I agree, we should collaborate and find a resolution.
upvoted 0 times
...
Shawna
2 months ago
A: Let's try to work out a solution together as a team.
upvoted 0 times
...
...
Sharee
3 months ago
I agree with Simona, the team should work together to find a solution.
upvoted 0 times
...
Simona
3 months ago
I think the scrum master should ask the team to collaboratively work out a solution.
upvoted 0 times
...
Bettina
3 months ago
Option B is tempting, but the Scrum Master shouldn't be the one solving problems. That's the team's responsibility.
upvoted 0 times
Janna
2 months ago
D) Engage a technical manager to assist with finding a solution
upvoted 0 times
...
Mira
2 months ago
A) Consider adding a story to the next sprint to seek resolution
upvoted 0 times
...
Brittni
2 months ago
C) Ask the team to collaboratively work out a solution
upvoted 0 times
...
Floyd
3 months ago
D) Engage a technical manager to assist with finding a solution
upvoted 0 times
...
Jesus
3 months ago
C) Ask the team to collaboratively work out a solution
upvoted 0 times
...
...
Tish
3 months ago
I'd go with Option A. Adding a story to the next sprint gives us time to properly address the issue without disrupting the current plans.
upvoted 0 times
...
Franchesca
3 months ago
Option C is the way to go. The team should work together to find a solution - that's the whole point of Scrum!
upvoted 0 times
Queenie
3 months ago
A) Consider adding a story to the next sprint to seek resolution
upvoted 0 times
...
Denise
3 months ago
C) Ask the team to collaboratively work out a solution
upvoted 0 times
...
...

Save Cancel