Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 1 Question 95 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 95
Topic #: 1
[All PMI-ACP Questions]

An agile team member identifies a potential problem within the project team How should the team's coach react?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Monroe
6 days ago
You know, if I was the coach, I'd probably just grab a cup of coffee and let the team work it out. They're the Agile experts, right?
upvoted 0 times
...
Meaghan
7 days ago
Haha, I bet the project manager would love to get that escalation! Option A is a bit overkill if you ask me.
upvoted 0 times
...
Geoffrey
8 days ago
Hmm, I'm torn between B and C. Putting it in the backlog could work, but the team should definitely try to figure it out first.
upvoted 0 times
...
Sunny
30 days ago
I don't know, I think Option D makes more sense. The coach should really get to the root of the issue and involve the product owner.
upvoted 0 times
...
Bo
1 months ago
I believe adding the problem to the backlog and assigning it to a future iteration could also be a good approach. It allows the team to prioritize and address it in a timely manner.
upvoted 0 times
...
Deeann
1 months ago
Option C is the way to go! The team should try to solve the problem themselves - they're the experts after all.
upvoted 0 times
Franklyn
8 days ago
B) Add the problem to the backlog and assign resolution to a future iteration
upvoted 0 times
...
Rodrigo
12 days ago
A) Document the problem escalate to the project manager, and develop a solution for the team
upvoted 0 times
...
Brett
19 days ago
C) Instruct the team to try to solve the problem within the team
upvoted 0 times
...
...
Wilda
1 months ago
I agree with Tran. It's important to involve the project manager to ensure the problem is addressed properly.
upvoted 0 times
...
Tran
1 months ago
I think the coach should document the problem and escalate it to the project manager.
upvoted 0 times
...

Save Cancel