Actual exam question for PMI's PMI-100 exam
Question #: 60
Topic #: 1
[All PMI-100 Questions]

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Show Suggested Answer Hide Answer
Suggested Answer: D