Several issues are identified on one component project in a program. During a meeting with that component's project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.
What should the program manager do?
Jeanice
29 days agoRose
30 days agoRoy
1 months agoMariann
10 days agoDalene
1 months agoJanna
17 days agoNgoc
19 days agoKyoko
2 months agoReena
14 days agoKenny
19 days agoTony
1 months agoKristel
2 months agoSerina
2 months agoMaxima
3 months ago