Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 6 Question 80 Discussion

Actual exam question for PMI's PgMP exam
Question #: 80
Topic #: 6
[All PgMP Questions]

Several issues are identified on one component project in a program. During a meeting with that component's project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.

What should the program manager do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Maxima
1 days ago
I think the program manager should join project-level issue resolution meetings.
upvoted 0 times
...

Save Cancel