Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 6 Question 64 Discussion

Actual exam question for PMI's PgMP exam
Question #: 64
Topic #: 6
[All PgMP Questions]

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B.

This is an example of which of the following?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel