Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 6 Question 63 Discussion

Actual exam question for PMI's PgMP exam
Question #: 63
Topic #: 6
[All PgMP Questions]

One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set.

If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel