BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 6 Question 59 Discussion

Actual exam question for PMI's PgMP exam
Question #: 59
Topic #: 6
[All PgMP Questions]

During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.

Which will provide the greatest value to clarify stakeholder perceptions?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel