Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 6 Question 11 Discussion

Actual exam question for PMI's PgMP exam
Question #: 11
Topic #: 6
[All PgMP Questions]

A program manager is responsible for constructing a US$50 million building. Management suggests it will take three years to complete. The program manager can select a design-build option to optimize the construction schedule to 1.5 years. However, heavy demand for steel is causing price increases and delivery delays. If this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1.25 years.

What is the expected time of delivery?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel