Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 4 Question 71 Discussion

Actual exam question for PMI's PgMP exam
Question #: 71
Topic #: 4
[All PgMP Questions]

A large infrastructure development program involves three road construction projects, two sewage line construction projects, and one project to lay underground electric cables. During a program meeting, the project manager of a road construction project communicates that a project risk related to the interdependency with a sewage line project has crossed its risk threshold.

What should the program manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Crista
5 months ago
It's crucial to get the program sponsor involved in case the risk has a big impact on the overall program.
upvoted 0 times
...
Marshall
6 months ago
I believe instructing the project manager to escalate the risk to the program sponsor is the best option.
upvoted 0 times
...
Salome
6 months ago
That could work too, as long as the risk is properly managed.
upvoted 0 times
...
Crista
6 months ago
But what about incorporating the risk into the program risk response strategy?
upvoted 0 times
...
Marshall
6 months ago
I agree with Salome, it's important to address the risk now.
upvoted 0 times
...
Salome
6 months ago
I think the program manager should modify the program schedule.
upvoted 0 times
...
Darrin
6 months ago
I see your point. It's all about managing the risk effectively at the program level.
upvoted 0 times
...
Tricia
6 months ago
That's a good point. It's important to have a comprehensive risk response strategy.
upvoted 0 times
...
Tamekia
7 months ago
I disagree. I think they should incorporate the project risk into the program risk response strategy.
upvoted 0 times
...
Darrin
7 months ago
I think they should modify the program schedule to accommodate the risk.
upvoted 0 times
...
Tricia
7 months ago
Yeah, that's concerning. What do you think the program manager should do?
upvoted 0 times
...
Darrin
7 months ago
I heard about the project risk in the road construction project.
upvoted 0 times
...
Elouise
8 months ago
Ooh, good point! The program manager needs to be proactive here. I'm torn between options A and B. Modifying the schedule could work, but integrating it into the overall risk response might be the more sustainable approach.
upvoted 0 times
...
Florencia
8 months ago
Hmm, I'm not so sure. Escalating to the sponsor feels like passing the buck a bit. I think the program manager should be taking a more active role here, either by modifying the schedule or incorporating the risk into the overall program strategy.
upvoted 0 times
Mariann
8 months ago
A) Modify the program schedule to accommodate the risk.
upvoted 0 times
...
Julieta
8 months ago
B) Incorporate the project risk into the program risk response strategy.
upvoted 0 times
...
Tomoko
8 months ago
A) Modify the program schedule to accommodate the risk.
upvoted 0 times
...
Lenita
8 months ago
B) Incorporate the project risk into the program risk response strategy.
upvoted 0 times
...
Noble
8 months ago
A) Modify the program schedule to accommodate the risk.
upvoted 0 times
...
...
Edna
8 months ago
I agree, this is a tricky one. I'm leaning towards option C, escalating the risk to the program sponsor. That seems like the best way to get some high-level support and oversight to manage this interdependency issue.
upvoted 0 times
...
Paris
8 months ago
Whoa, this question is really testing our understanding of program management! The key here is to figure out how the program manager should handle the risk that's crossed the threshold in the road construction project.
upvoted 0 times
...

Save Cancel