BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 4 Question 53 Discussion

Actual exam question for PMI's PgMP exam
Question #: 53
Topic #: 4
[All PgMP Questions]

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting.

What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel