Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 3 Question 76 Discussion

Actual exam question for PMI's PgMP exam
Question #: 76
Topic #: 3
[All PgMP Questions]

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind

schedule. Based on this information, what is the schedule performance index (SPI) for this program?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Reita
1 days ago
I agree with Vincent, because SPI is calculated by dividing percent complete by percent planned, which in this case is 30% / 35% = .86
upvoted 0 times
...
Vincent
2 days ago
I think the answer is B) .86
upvoted 0 times
...

Save Cancel