PMI Exam PgMP Topic 3 Question 28 Discussion

Actual exam question for PMI's PgMP exam
Question #: 28
Topic #: 3
[All PgMP Questions]

A municipal agency manages a city's water and wastewater infrastructure. Its six-year capital improvement program (CIP) is approximately US$4 billion, and is used for such things as improving aging infrastructure, addressing regulatory requirements, and upgrading facilities. The mayor and key stakeholders are concerned because of yearly rate increases for residents. After receiving proposals from program managers for this key program, which is half of the current CIP, a program management team is hired and receives an approved business case.

What should the project manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B