BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 3 Question 23 Discussion

Actual exam question for PMI's PgMP exam
Question #: 23
Topic #: 3
[All PgMP Questions]

The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requirements six months into a three-year program.

What should the program manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel