A program with 10 components is in the planning phase. Project managers who oversee the component projects request detailed schedules. These schedules will be merged into one document to create a master schedule.

What should the program manager do to ensure that the overall program life cycle will meet stakeholder needs and deliver planned benefits?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Rolande
1 months ago
Haha, the other options sound like something my grandpa would suggest. Option D is the way to go, keep it simple and use a WBS!
upvoted 0 times
...
Emerson
1 months ago
Option D all the way! I'm surprised the other options are even there. A WBS is the way to go, no doubt about it.
upvoted 0 times
...
Elouise
1 months ago
Option D is the clear winner. Decomposing schedules is good, but a WBS will give the program manager a complete picture to manage the entire program effectively.
upvoted 0 times
Amber
9 days ago
D) Create a work breakdown structure (WBS) to align program execution with stakeholder expectations and the benefits management plan
upvoted 0 times
...
Beula
26 days ago
A) Establish a quality review for the project schedules to ensure that resource leveling and baselines are followed and component projects are delivered on time
upvoted 0 times
...
...
Vincenza
2 months ago
I believe creating a work breakdown structure (WBS) would also help align program execution with stakeholder expectations.
upvoted 0 times
...
Halina
2 months ago
I agree with Stephen. It's important to follow resource leveling and baselines to meet stakeholder needs.
upvoted 0 times
...
Ceola
2 months ago
I agree, a WBS is crucial to keep the program on track and deliver the planned benefits. Option D is the way to go here.
upvoted 0 times
...
Pedro
2 months ago
Option D seems the most comprehensive approach to align the program with stakeholder needs. Establishing a quality review and decomposing schedules are good, but a WBS is key to ensuring overall program execution meets expectations.
upvoted 0 times
Gracie
28 days ago
C: Yeah, establishing a quality review and decomposing schedules are important, but a WBS is what ties everything together.
upvoted 0 times
...
Hillary
29 days ago
B: I agree, a WBS is crucial for ensuring the program delivers planned benefits.
upvoted 0 times
...
Florencia
2 months ago
A: Option D is definitely the way to go. A WBS will really help align everything with stakeholder expectations.
upvoted 0 times
...
...
Stephen
2 months ago
I think the program manager should establish a quality review for the project schedules to ensure that component projects are delivered on time.