PMI Exam PgMP Topic 2 Question 77 Discussion

Actual exam question for PMI's PgMP exam
Question #: 77
Topic #: 2
[All PgMP Questions]

The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.

What should the program manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Sena
5 months ago
True, a contingency reserve is more comprehensive. Finalizing with B.
upvoted 0 times
...
Karima
5 months ago
Could be, but avoiding threats doesn’t always account for unforeseen problems.
upvoted 0 times
...
Oren
5 months ago
But shouldn’t we avoid known critical project threats first? Option C?
upvoted 0 times
...
Horace
6 months ago
Yeah, a contingency reserve can cover unexpected issues. Sounds logical.
upvoted 0 times
...
Sena
6 months ago
I think establishing a contingency reserve makes sense, so option B.
upvoted 0 times
...
Karima
6 months ago
Interesting question. What should the program manager do next?
upvoted 0 times
...