Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 2 Question 74 Discussion

Actual exam question for PMI's PgMP exam
Question #: 74
Topic #: 2
[All PgMP Questions]

A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.

What should the program manager do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Lawrence
1 days ago
I think the program manager should select the best bid from the prequalified vendor list.
upvoted 0 times
...

Save Cancel