PMI Exam PgMP Topic 2 Question 36 Discussion

Actual exam question for PMI's PgMP exam
Question #: 36
Topic #: 2
[All PgMP Questions]

A program manager joins a team to fix a troubled enterprise-wide customer relationship management (CRM) system. Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository for similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity.

What should the program manager do with the knowledge gained from this activity?

Show Suggested Answer Hide Answer
Suggested Answer: D