Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 1 Question 92 Discussion

Actual exam question for PMI's PgMP exam
Question #: 92
Topic #: 1
[All PgMP Questions]

During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.

What should the program manager do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Mariann
2 months ago
Ah, the classic 'work more, don't bill' option. Classic project manager move right there. I bet the team would love that! 'Hey guys, we need you to put in some unpaid overtime. No, I don't have a raise for you, but think of the exposure!'
upvoted 0 times
Lashawn
4 days ago
D) Talk with the project manager and find ways to reduce hours in another part of the project.
upvoted 0 times
...
Mariann
13 days ago
B) Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.
upvoted 0 times
...
Frederica
26 days ago
D) Talk with the project manager and find ways to reduce hours in another part of the project.
upvoted 0 times
...
Reita
29 days ago
A) Communicate to the program sponsor regarding the additional estimated cost and request a change order.
upvoted 0 times
...
Fidelia
29 days ago
B) Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.
upvoted 0 times
...
Narcisa
1 months ago
A) Communicate to the program sponsor regarding the additional estimated cost and request a change order.
upvoted 0 times
...
...
Hillary
2 months ago
Option D sounds tempting, but I'm not sure how realistic it is to find ways to reduce hours 'in another part of the project'. That could create more problems than it solves. Better to be upfront and get the sponsor's approval.
upvoted 0 times
...
Malinda
2 months ago
I agree with Yvonne. Requesting a change order is the proper way to handle this situation. Trying to find 'excess capacity' or asking the team to work extra hours without compensation is not a good long-term solution.
upvoted 0 times
Dierdre
24 days ago
I agree, requesting a change order is the best approach in this situation.
upvoted 0 times
...
Ashlyn
26 days ago
D) Talk with the project manager and find ways to reduce hours in another part of the project.
upvoted 0 times
...
Malinda
27 days ago
B) Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.
upvoted 0 times
...
Leatha
28 days ago
B) Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.
upvoted 0 times
...
Nobuko
29 days ago
A) Communicate to the program sponsor regarding the additional estimated cost and request a change order.
upvoted 0 times
...
Timothy
2 months ago
A) Communicate to the program sponsor regarding the additional estimated cost and request a change order.
upvoted 0 times
...
...
Yvonne
2 months ago
Option A is the best choice here. Transparency and communication with the program sponsor is crucial when dealing with budget overruns. Trying to hide or redistribute the additional hours could backfire down the line.
upvoted 0 times
...
Ahmad
2 months ago
I think talking with the project manager to find ways to reduce hours in another part of the project could also be a good solution.
upvoted 0 times
...
Brock
2 months ago
I agree with Rosendo. It's important to keep the sponsor informed about any budget changes.
upvoted 0 times
...
Rosendo
3 months ago
I think the program manager should communicate to the program sponsor regarding the additional estimated cost and request a change order.
upvoted 0 times
...

Save Cancel