Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 1 Question 70 Discussion

Actual exam question for PMI's PgMP exam
Question #: 70
Topic #: 1
[All PgMP Questions]

When should a program manager approve the closure of a component project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Lynsey
8 months ago
I'm with Darci on this one. D is the way to go. We don't want the program manager approving project closure before the actual work is done, do we? That would be a recipe for disaster.
upvoted 0 times
...
Glory
8 months ago
You both make good points. But I'm going with C, when program deliverables are complete. The program manager is responsible for the overall program, not just the individual projects.
upvoted 0 times
...
Keneth
8 months ago
I disagree. I think the correct answer is B, when the project has delivered the project benefits. That's the whole point of the project, isn't it? To deliver the benefits, not just the deliverables.
upvoted 0 times
Tashia
8 months ago
B) When the project has delivered the project benefits
upvoted 0 times
...
Augustine
8 months ago
I disagree. I think the correct answer is B, when the project has delivered the project benefits. That's the whole point of the project, isn't it? To deliver the benefits, not just the deliverables.
upvoted 0 times
...
Alayna
8 months ago
A) When acceptance criteria of the project are met
upvoted 0 times
...
...
Darci
8 months ago
Hmm, this is a tricky one. I think the right answer is D, when project deliverables are complete. The project manager's job is to ensure the project is delivered, not necessarily the program benefits.
upvoted 0 times
...

Save Cancel