Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 1 Question 40 Discussion

Actual exam question for PMI's PgMP exam
Question #: 40
Topic #: 1
[All PgMP Questions]

A program with 10 components is in the planning phase. Project managers who oversee the component projects request detailed schedules. These schedules will be merged into one document to create a master schedule.

What should the program manager do to ensure that the overall program life cycle will meet stakeholder needs and deliver planned benefits?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel